East Texas construction projects for the week of Nov. 13

East Texas construction projects for the week of Nov. 13

Released by the Texas Department of Transportation: 

TYLER – Here's a look at work planned in the district during the Week of Nov. 13, 2017. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Slow down and pay attention when traveling through work zones.

Motorists should prepare for a major change tentatively set for this week to move traffic on US 79 in Palestine to its permanent configuration, weather permitting. All northbound traffic will be moved to the newly completed northbound travel lanes with all southbound traffic utilizing the southbound lanes. A new traffic pattern will also be implemented on FM 645 requiring those wanting to head north to proceed under the new overpasses. FM 645 motorists must stop at Stop Signs installed on both sides of the overpasses and at the exit ramps to FM 645. Southbound traffic will use the ramp to reach the southbound lanes of US 79. Additionally, SH 294 traffic will have access to the new deceleration and acceleration lanes. Additional project information is available below.

On the US 175 Phase III project from Poynor to Frankston, traffic will be detoured from CR 300 to CR 303 next week from 8 a.m. to 4:30 p.m. as construction crews work on tying the intersection of CR 300 into the newly constructed westbound lanes on US 175.  Signing and flaggers will be used to direct traffic when traffic is being detoured to CR 303. The detour is 1.2 miles long and may increase the drivers trip by about 3 minutes. We appreciate your patience and support as we work swiftly to complete this work. This project is located in Anderson County but is grouped with the US 175 projects in the Henderson County section of this release.

The westbound outside lane of I-20 and the FM 314 Westbound Exit Ramp in Van Zandt County will be closed Tuesday, November 14, as the contractor loads and moves concrete traffic barriers in preparation of starting the next phase of the ramp relocation project. Get more information on this I-20 project in the Van Zandt County section of this release.

In Smith County, daily lane closures remain in effect on I-20 eastbound and westbound at Toll 49 as the contractor for the Lindale Relief Route conducts work to install deck panels and overhangs of the Toll 49 Mainlane Bridge. Work is progressing from south to north through about November 17th. The contractor will be closing lanes starting with the eastbound outside lane. Local law enforcement will be on site to assist with traffic control. No lane closures are allowed after noon on Friday’s.  

Anderson County – Palestine Maintenance plans to conduct edge maintenance on FM 19 between Neches and Frankston. Expect lane closures with flaggers providing traffic control.

Anderson County construction projects updates:

US 79 New Lane Construction Project

  • style="color:black;">Limits: From 1.6 miles southwest of Loop 256 in Palestine south to the Trinity River
  • style="color:black;">Contractor: Longview Bridge and Road, Ltd., of Longview
  • style="color:black;">Cost: $42.7 million
  • style="color:black;">Anticipated Completion Date: Winter 2017

A major traffic switch is planned for the project this week to separate northbound and southbound traffic, moving them to their permanent traffic pattern. Ongoing work consists of applying permanent striping, placing driveways, and mow strips for Metal Beam Guard Fence. Expect lane closures. Motorists should be prepared for a major traffic switch the Week of November 13. The project is expanding a 5.3 mile section of US 79 from two lanes to a four-lane divided highway with a continuous left turn lane and a depressed median.

SH 19 Widening Project

  • style="color:black;">Limits: From 3.6 miles N of FM 837 (Henderson Co. line) south to .4 mile N of FM 321 at Montalba
  • style="color:black;">Contractor: Big Creek Construction of Hewitt
  • style="color:black;">Cost: $12.5 million
  • style="color:black;">Anticipated Completion Date: Winter 2017

Hot mix operations get underway this week for the widening of the northbound lanes. Motorists should remain alert when traveling through the work where trucks will be entering and exiting, causing slow-downs in traffic movement. This project is widening the roadway with the addition of shoulders and passing lanes. The posted speed limit is 55 mph. Expect delays and multiple lane closures with flaggers and a pilot car controlling traffic.

Off-System Bridge Replacement Project

  • style="color:black;">Limits: County Road 458 at Beaver Creek and County Road 2418 at Otter Creek
  • style="color:black;">Contractor: Longview Bridge and Road Ltd., of Longview
  • style="color:black;">Anticipated Completion Date: Winter 2017

County Road 2418 is closed at Otter Creek for a bridge replacement project. The contractor is tying steel, forming the abutments with a concrete pour scheduled.

Cherokee County – Jacksonville and Rusk maintenance crews plan to clean the inside shoulders of US 69 at Seven Mile Hill south of Jacksonville. Crews will also perform base repairs on FM 2493 and FM 851. Expect lane closures with flaggers providing traffic control at the various locations.

Cherokee County construction projects updates:

US 69 Widening through Wells

  • style="color:black;">Limits: From 2 miles north of FM 1247 in Wells, south to 0.9 mile south of FM 1247
  • style="color:black;">Contractor: Longview Bridge and Road, Ltd., of Longview
  • style="color:black;">Cost: $17.6 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

The contractor is building a detour and installing culverts. The project is widening US 69 through Wells from two lanes to four lanes with new curb and gutter and a two-way left turn lane through town. There are minimal impacts to traffic. The speed limit has been reduced on the northern end of the project until work is completed.

US 79 Repairs and Resurfacing Project

  • style="color:black;">Limits: From SH 204 to Mud Creek
  • style="color:black;">Contractor: Reynolds & Kay
  • style="color:black;">Cost: $5.7 million
  • style="color:black;">Anticipated Completion Date: Fall 2017

Cleanup work is ongoing. Expect lane closures for the duration of the project when construction equipment is near the travel lanes. The speed limit is reduced along project limits.

FM 22 Safety Treatment Project

  • Limits: From 1.5 MI W of FM 768, E to SH 110
  • Contractor: Highway 19 Construction
  • Cost: $1 million
  • Anticipated Completion Date: Fall 2017

Drainage work continues on this project to treat fixed objects for safety. Expect lane closures.

Gregg County – Longview Maintenance plans to place a hot mix overlay on FM 2275 between FM 3272 and FM 1845. Expect lane closures with flaggers and a pilot car providing traffic control.

Gregg County construction projects updates:

Landscape Improvement Project

  • Limits: Loop 281 at SH 300/Gilmer Rd and Loop 281 at Fourth St.
  • Contractor: Central North Construction, LLC
  • Cost: $224,600
  • Anticipated Completion Date: February 2018

This project consists of landscaping improvements in Gladewater, Kilgore, Longview and White Oak. Work includes irrigation, planter beds, and installing various plants. The contractor will also work on existing beds on I-20 in Longview and on SH 42 in Kilgore. New landscaping beds will be installed in White Oak on US 80, in Gladewater on Loop 485, in Longview at SH 300 and Loop 281 as well as Fourth St. and Loop 281, and on SH 322 in Henderson. All work is in the right of way. No traffic delays are expected.

Turn Lanes Project

  • Limits: US 259 at Hawkins Parkway; Loop 281 at Hollybrook Drive
  • Contractor: Longview Bridge and Road, Ltd., of Longview
  • Cost: $457,500
  • Anticipated Completion Date: Fall 2017

Drainage work is ongoing at the Loop 281 - Hollybrook Drive intersection as work continues to add turn lanes on Loop 281. The inside lanes of the loop will be closed at Hollybrook Drive. The project consists of earthwork, base, asphaltic concrete pavement (ACP) surface, signing and pavement markings.                                               

US 80 Widening in Gladewater

  • style="text-align:justify;">Limits: Loop 485 to Locker Plant Road.
  • style="text-align:justify;">Contractor: Longview Bridge and Road
  • style="text-align:justify;">Cost: $3.54 million
  • style="text-align:justify;">Anticipated Completion Date: Spring 2018

Storm sewer work continues on the south side of the roadway with eastbound traffic reduced to one lane. The project consists of widening US 80 to four through lanes with a left turn lane from Loop 485 to Locker Plant Road. Work includes earthwork, base and surface work, storm sewer, concrete curb and gutter, safety improvements, and upgrading signage and pavement markingsMotorists can expect delays and lane closures during this work.

Loop 281 at FM 1845/Pine Tree Road

  • style="color:black;">Limits: From US 80 to Shofner Drive
  • style="color:black;">Contractor: Longview Bridge and Road, Ltd., of Longview
  • style="color:black;">Cost: $4.54 million
  • style="color:black;">Anticipated Completion Date: January 2018

Work is ongoing to install storm sewer and cement treat base material. Traffic is reduced to one travel lane in all directions. Alternate routes are recommended on this project where work is being conducted in multiple phases that could require overnight lane closures. The project includes widening the roadway, installing storm drain, grading and base work, curb and gutter, raised medians, surface, signs and pavement markings.

FM 2275 George Richey Extension (Segment I)

  • Limits: From McCann Road west to SH 300 (Gilmer Road)
  • Contractor: East Texas Bridge, Inc.
  • Cost: $12.4 million
  • Anticipated Completion Date: Fall 2017

With the project winding down, the contractor continues to work on punch list items. The project includes constructing two bridges and a four-lane roadway with center left turn lanes from McCann Road to SH 300/Gilmer Road. It also includes applying a hot mix asphalt surface, curb and gutter as well as sidewalk.

SH 149 at Sabine River

•       Limits: SH 322 to approximately one half mile north of the Sabine River Bridge

•      Contractor: Gibson and Associates

•      Cost: $3.1 million

•      Anticipated Completion Date: Spring 2018

Contractor will be installing guardrail on I-20 near the Smith County line this week. The outside lane will be closed for eastbound and westbound traffic. Expect closures and delays. The project consists of constructing new guardrail and sidewalk on the bridge and increasing its load carrying capacity.                                                                                                               

Henderson County – Athens Maintenance plans to conduct surface repairs on FM 317 and edge work on FM 59. Expect lane closures with flaggers providing traffic control.

Henderson County construction projects updates:

SH 19 Widening Project

  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Limits: FM 1615 South to 0.3 mile south of Coon Creek
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Contractor: A.L. Helmcamp
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Cost: $ 4.95 million
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Anticipated Completion Date: Spring 2019

Work continues to set driveway pipes and extend cross structures on this job. Daily lane closures can be expected with a pilot vehicle providing traffic control. The speed limit has been reduced to 60 mph for the duration of the project which consists of adding 10-foot shoulders on both the northbound and southbound travel lanes. 

US 175 Widening Project (Phase I)

  • style="color:black;">Limits: From 0.1 mile SE of FM 804 near Baxter SE to 1.1 miles E of Loop 60E at Larue
  • style="color:black;">Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
  • style="color:black;">Cost: $39.2 million
  • style="color:black;">Anticipated Completion Date: November 2018

Caution is advised as work continues to widen structures on the old roadway near Baxter and Larue. Crews will also be hauling materials for the new westbound roadway in Baxter. Motorists should remain alert as construction equipment enters and exits the roadway throughout the work day. The speed limit is 55 mph on this project to expand US 175 from two lanes to a four-lane divided highway with a depressed median.

US 175 Widening Project (Phase II)

  • style="color:black;text-align:justify;">Limits: From 1.1 miles E of Loop 60B at Larue to 0.85 mile E of FM 315 at Poynor
  • style="color:black;text-align:justify;">Contractor: Sundt Construction, Inc., of San Antonio
  • style="color:black;text-align:justify;">Cost: $37.8 million
  • style="color:black;text-align:justify;">Anticipated Completion Date: Winter 2017

The eastern most access to FM 315 and downtown Poynor remains closed while culvert work and permanent construction of the roadway continues. Motorists must use the western most access for FM 315 and Poynor. Meanwhile, hot mix and seal coat operations are being conducted on the westbound travel lanes. A traffic switch is tentatively set for the week of November 27 to move westbound traffic to its new lanes. Construction of the culvert headwalls is ongoing. A short stretch of CR 4401 is permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 is open with access from CR 4354/Camp Rd.

This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This, like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.

US 175 Widening Project (Phase III) in Anderson County

  • style="color:black;">Limits: From 0.85 mile E of FM 315 in Poynor SE to .5 mile NW of SH 155 at Frankston
  • style="color:black;">Contractor: A.L. Helmcamp, Inc.
  • style="color:black;">Cost: $27.6 million
  • style="color:black;">Anticipated Completion Date: Spring 2019

Traffic will be detoured from CR 300 to CR 303 next week from 8 a.m. to 4:30 p.m. as crews work to tie the intersection of CR 300 into the new US 175 westbound lanes. Look for flaggers and signage in place to direct traffic to the CR 303 detour. Meanwhile, the contractor is maintaining storm water control measures throughout the project limits. Earthwork operations are ongoing along with hot mix asphalt application from County road 301 to County Road 303. Lane closures are possible on this project that’s expanding US 175 from two lanes to a four-lane divided highway with a depressed median.

Rusk County – Henderson Maintenance continues hot mix overlay operations on FM 1251 this week from FM 2658 to the Panola County line. Expect one lane carrying two-way traffic with flaggers and a pilot car providing traffic control.

Rusk County construction projects updates:

SH 43 Overlay Project

  • style="color:black;">Limits: From US 79 (at the Star) to 9.9 miles toward Tatum at CR 2136
  • style="color:black;">Contractor: Madden Contracting Company, LLC
  • style="color:black;">Cost:  $4.6 million
  • style="color:black;">Anticipated Completion Date: Fall 2017

The contractor is working on punch list items as the project nears completion. The project includes applying an asphalt overlay and new striping, base repairs, and installing new metal beam guard fence.

ADA Ramp Installations (Notice of Project Completion)

  • style="color:black;">Limits: In Overton - SH 135 from SH 323 to McKay St; FM 850 from Rusk St. to Neal St.
  • style="color:black;">Limits: In Henderson - Business 64/Marshall Ave. from Van Buren St. to Redbud St.; Business 79/Main St. from College St. to Oak Street; FM 13/West Main St. from Standish St. to Jackson St.
  • style="color:black;">Contractor: Ti-Zack Concrete, Inc., of Minnesota
  • style="color:black;">Cost: $1.4 million
  • style="color:black;">Anticipated Completion Date: Fall 2017

Project work to install sidewalks and ramps on roadways in Henderson and Overton has been completed but work continues on punch list items. Work includes removing the existing and building new ramps, sidewalks, hand rails and curb and gutter.

Smith County – Tyler Maintenance plans to conduct fog seal operations on FM 14 between FM 16 and the Wood County line. A second crew will continue base repair work in Derrick Park before moving to Loop 124 later in the week. Expect lane closures with flaggers providing traffic control in both work zones.

Smith County construction projects updates:

FM 850 Bridge Replacement Project (New Project)

  • style="color:black;">Limits: FM 580 at Mud Creek just east of FM 21
  • style="color:black;">Contractor: Stateline Construction
  • style="color:black;">Cost: $1.1 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

The contractor is currently removing the existing structure and will start work on embankment and drill shafts. The road is closed at Mud Creek with traffic detoured. The project will replace the existing bridge with a wider one. 

SH 64E Resurfacing Project

  • Limits: From Loop 323 to 1.7 miles southeast of Spur 248

•      Contractor: Madden Contracting Company, LLC

•      Cost: $3.6 million

•      Anticipated Completion Date: Fall 2017

Striping work is expected to get underway this week. The project consists of making repairs to the curb and gutter across from Brookshire’s on SH 64 just east of Loop 323 and placing a new surface from the loop to Chapel Hill.

SH 64W Resurfacing Project

•      Limits: From Loop 323 to 0.7 miles west of FM 724

•      Contractor: IOC Company of Edinburg, TX

•      Cost: $1.7 million

•      Anticipated completion date: Fall 2017

Cleanup operations continue on this project from Loop 323 to just past Tyler Pounds Airport. Expect lane closures and possible delays.

SH 31E Widening Project

  • style="color:black;">Limits: From FM 757 to FM 2012
  • style="color:black;">Contractor: Reynolds & Kay, LTD
  • style="color:black;">Cost: $7.8 million
  • style="color:black;">Anticipated Completion Date: Fall 2017

Cleanup activities are being conducted. Expect lane closures with flaggers providing traffic control. The speed limit during work hours is 60 mph.

SH 31E Overlay Project

  • style="color:black;">Limits: From Loop 323 to FM 850
  • style="color:black;">Contractor: Reynolds & Kay, LTD
  • style="color:black;">Cost: $1.8 million
  • style="color:black;">Anticipated Completion Date: Fall 2017

Cleanup work is underway on this project where a Porous Friction Course (PFC) surface has been applied. Expect lane closures. 

US 271 Mill and Inlay Project

  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Limits: From 0.4 miles south of Spur 147 at Oakwood St., south to SH 64/Fifth St. in Tyler
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Contractor: Clark Construction of Texas, Inc. from San Antonio
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Cost: $2.1 million
  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Anticipated Completion Date: Fall 2017

No work is planned for this night time project that consists of base repairs, planing, applying a hot mix surface and striping. When work resumes it will be conducted between the hours of 7:30 p.m. and 6 a.m.

Spur 248 Widening Project

  • style="color:black;">Limits: From 1.75 miles west of FM 848/Old Omen Road going east to SH 64 southeast of Tyler
  • style="color:black;">Contractor: Lonestar Equipment Company, Inc.
  • style="color:black;">Cost: $8.6 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

Work on the north side of the roadway will continue and includes embankment and drainage structures. Expect lane closures with flaggers providing traffic control. The speed limit is 55 mph during construction to widen Spur 248 from two lanes to a four-lane divided roadway with flush median.

I-20 Resurfacing Project

  • Limits: From US 69 to FM 14 WB only
  • Contractor: Clark Construction
  • Cost: $2.9 million
  • Anticipated Completion Date: Fall 2017

Paving operations are ongoing in the westbound lanes. This project is placing a new Porous Friction Course (PFC) surface in the westbound lanes and installing upgrades to the metal beam guard fence along this stretch of I-20.

Turn Lanes Project

  • style="color:black;">Limits: Various locations throughout Tyler
  • style="color:black;">Contractor: Lonestar Equipment Company, Inc.
  • style="color:black;">Cost: $2.4 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

Work continues on US 69/Broadway and South Town Drive to remove the concrete curb and gutter and backfill the existing pavement. Expect lane closures and delays with flaggers providing traffic control.

The project is removing the existing medians to extend the turn lanes, and adding right turn lanes to various intersections in Tyler. Work will be conducted on US 69, Cumberland Road, Independence, South Donnybrook, Rice, South Town and wrap up at Grande and FM 2493.

Tyler State Park

•      Limits: Inside Tyler State Park

  • style="font-size:11pt;font-family:Calibri, sans-serif;color:black;">Contractor: A.L. Helmcamp, Inc. of Buffalo

•      Cost: $1.2 million

•      Anticipated Completion Date: Winter 2017

This project is occuring inside the park. Check the park website for public notifications.

Van Zandt County – Canton Maintenance plans to conduct mill and inlay operations first on SH 19S, then moving to US 80 between SH 19 and Fruitvale. Expect lane closures at both locations with flaggers providing traffic control.

Van Zandt County construction projects updates:

I-20 Westbound Exit Ramp at FM 314 Relocation Project

  • style="color:black;">Limits: From FM 314 WB Exit Ramp and Frontage Road
  • style="color:black;">Contractor: Longview Bridge and Road, Ltd., of Longview
  • style="color:black;">Cost: $4.6 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

Expect the westbound outside lane and FM 314 Exit Ramp to be closed Tuesday as the contractor loads and moves concrete traffic barriers. Meanwhile, concrete pavement and driveway work continue on the Westbound Frontage Road. The contractor continues Phase III work, removing concrete pavement on the frontage road east of the I-20 Exit Ramp. The Westbound Frontage Road is closed at CR 4930. Motorists can expect minimal delays. Alternate routes are encouraged. The project consists of reconstructing the frontage road and building a new exit ramp 1.13 miles east of FM 314.

I-20 Safety Work

  • Limits: From Kaufman County Line going east to SH 19, etc.
  • Contractor: FNH Construction, LLC
  • Cost: $2.4 million
  • Anticipated Completion Date: Fall 2018

The contractor is removing and installing Metal Beam Guard Fence and concrete mow strip along the westbound outside lane going west from SH 19 toward the Kaufman County line. Expect lane closures and delays.

SH 243 Widening Project

  • Limits: From SH 198 east to SH 64 in Canton
  • Contractor: Longview Bridge and Road
  • Cost: $6.2 million
  • Anticipated Completion Date: June 2018

The contractor continues structure work on the north side of the road. Motorists can expect delays with a pilot vehicle and flaggers controlling traffic. This project is widening the roadway from two to four lanes with flush median, curb and gutter, and storm drain.

FM 314 Widening Project

  • style="color:black;">Limits: From I-20 to the Van Zandt/Henderson County line
  • style="color:black;">Contractor: A.L. Helmcamp, Inc., of Buffalo
  • style="color:black;">Cost: $11.9 million
  • style="color:black;">Anticipated Completion Date: Summer 2018

Work continues to shape ditches and install hot mix asphalt concrete driveways and intersections on the section five miles south of I-20. Guardrail work is slated to begin. Expect closures and delays with a pilot vehicle and flaggers controlling traffic.

FM 1256 Widening Project

  • style="color:black;">Limits: From FM 316 eastward to SH 19
  • style="color:black;">Contractor: Longview Bridge and Road, Ltd., of Longview
  • style="color:black;">Cost: $5.8 million
  • style="color:black;">Anticipated Completion Date: Fall 2018

No work is scheduled for the week on this project to widen the roadway.

FM 1861 Project

  • style="color:black;">Limits: From SH 19 to FM 2339
  • style="color:black;">Contractor: A.L. Helmcamp, of Buffalo, TX
  • style="color:black;">Cost: $2.44 million
  • Anticipated Completion Date: Fall 2018

No work is scheduled on this project.

FM 1652 Rehab Project

  • Limits: FM 17 south of Grand Saline, southward to FM 1255 northwest of Oakland
  • Contractor: Highway 19 Construction, LLC
  • Cost: $4.48 million
  • Anticipated Completion Date: Fall 2018

Cross structure and driveway work continue on the project. This phase of work will take several months to complete. Expect lane closures and delays with flaggers providing traffic control. The project is rehabilitating the road and consists of widening the existing roadway and structure work.

FM 1653 Rehab Project

  • Limits: SH 64 near Ben Wheeler, southwest to FM 858 at Martin Mills
  • Contractor: Drewery Construction Company, Inc., of Nacogdoches
  • Cost: $3.97 million
  • Anticipated Completion Date: Fall 2018

The contractor is conducting work on cross structures which will take several months to complete. Expect lane closures and delays. The project is rehabilitating the road and consists of widening the existing roadway and structure work.

Wood County – Mineola Maintenance plans to perform base repairs on SH 154 and FM 2966 this week.  Expect lane closures with flaggers providing traffic control.  

Wood County construction projects updates:

SH 182, etc., Safety Treating Project

  • style="color:rgb(31, 73, 125);">Limits: Various Roads - Current work on FM 2869 from FM 2088 south 8.12 miles to FM 49
  • style="color:black;">Contractor: Highway 19 Construction, LLC.
  • style="color:black;">Cost: $1.2 million
  • style="color:black;">Anticipated Completion Date: July 2017 for FM 2869; February 2018 for all work

Driveway, shaping ditches, installing top soil, and cross-culvert pipe extension work continues on FM 49. Minor delays are possible.

I-20 Total Maintenance Contract                                                  

•          Limits: Gregg, Smith and Van Zandt counties

•          Contractor: Firemen Excavation

Routine maintenance activities are ongoing on I-20 with moving operations throughout the week:

-           Debris Removal: Monday from the inside lane through all three counties

-           Debris Removal: Tuesday from the outside lane through all three counties

-           Large Sign Maintenance: Tuesday and Thursday through all three counties

-           Tree Removal: Throughout the week in Gregg and Smith counties

-           Herbicide Operations: Monday and Tuesday in Van Zandt County

-           Lane Closures: Van Zandt County all week – westbound between Mile Markers 523 and 530.