Tx-Dot work scheduled for week of Sept. 12

Released by the Department of Transportation:

TYLER – Here's a look at work planned in the district during the Week of Sept. 12, 2016. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are reminded to slow down and pay attention when traveling through work zones.

County Road (CR) 2138 at Blackhawk Creek near Whitehouse is set to close Monday in preparation for a bridge replacement project. Work to remove and replace the existing bridge is expected to begin on September 19. The closure will remain in place for about six months. Additional information about this work is in the Smith County section of this release.

Districtwide seal coat operations continue with work returning to FM 1861 in Henderson and Van Zandt counties Tuesday, weather permitting. The work limits are from FM 316 moving east to SH 19. The contractor then plans to move operations to SH 110 from FM 1255N going southeast to FM 18 in Van through Wednesday. The week winds down with work on US 69 from the Wood County line moving southeast to north of Lindale in Smith County. This will be daytime work conducted by the contractor, Brannan Paving Co., LTD, of Victoria, Texas.

The summer seal coat operation is the department’s preventive maintenance program that helps preserve roads by sealing them to keep water out, thereby, adding years of life to them, and lessening the required maintenance while providing a new driving surface for motorists. Seal coat applications are conducted on roads around the Tyler District’s eight counties. Motorists should bypass seal coat locations when possible to avoid delays.

ANDERSON COUNTY – Palestine Maintenance resumes work on southbound FM 59 at the intersection of FM 2961. Expect lane closures with flaggers providing traffic control.    

Anderson County construction projects updates:

US 79 New Lane Construction Project

•        Limits: 1.6 miles southwest of Loop 256 in Palestine south to the Trinity River

•        Contractor: Longview Bridge and Road, Ltd., of Longview.

•        Cost: $42.7 million

•        Anticipated Completion Date: End of 2016

Project work currently centers on the area from CR 2205 to just south of FM 645. The contractor is working on detours in the area of FM 645 at Tucker. This project expands a 5.3 mile section of US 79 from two lanes to a four-lane divided highway with a continuous left turn lane and a depressed median. Work started in November 2012.

SH 19 Widening Project

Limits: 3.6 miles north of FM 837 (Henderson Co. line) south to .4 mile north of FM 321 at Montalba

•        Contractor: Big Creek Construction of Hewitt

•        Cost: $12.5 million

•        Anticipated Completion Date: Summer 2017

Culvert, driveway and utility work is ongoing along the right of way where this roadway is being widened. Expect daily lane closures with flaggers providing traffic control. The posted speed limit is 55 mph.

Off-System Bridge Replacement Project

  • Limits: County Road (CR) 471 at Box Creek; CR 4801 at Indian Creek; CR 1231 at Stills Creek
  • Contractor: Longview Bridge and Road, Ltd., of Longview
  • Cost: $817,412.15
  • Anticipated Completion Date: Fall 2016

Work continues on the bridge replacement project on County Road 1231 at Stills Creek. The roadway is closed to traffic with detours in place. The new bridges at Box Creek and Indian Creek are open to traffic with the contractor continuing closeout activities.                                             

CHEROKEE COUNTY – Jacksonville Maintenance crews continue culvert work on US 69 south of Loop 456. Rusk Maintenance resumes channel and culvert cleaning activities on various roads around the county. Expect lane closures with flaggers providing traffic control at all work locations. 

Cherokee County construction projects updates:

US 69 Widening and Resurfacing

  • Limits: From Loop 456 in Jacksonville going south to just north of Loop 62 in Rusk
  • Contractor: Madden Contracting Company, LLC
  • Cost: $11 million
  • Anticipated Completion Date: Summer 2016

The contractor will be applying the final striping to the roadway this week. The project is widening US 69 by adding 2’ edge treatment and resurfacing the road. Expect lane closures.

US 69 Widening and Resurfacing

  • Limits: From 0.028 mile south of FM 343 in Rusk southward to just north of SH 21 in Alto
  • Contractor: Madden Contracting Company, LLC
  • Cost: $9.3 million
  • Anticipated Completion Date: Fall 2016

Seal coat work resumes requiring lane closures daily on this project to widen and resurface US 69.

US 69 Widening and Resurfacing

  • Limits: From .37 miles north of FM 344 to .02 miles north of FM 347
  • Contractor: Madden Contracting Company, LLC
  • Cost: $5.6 million
  • Anticipated Completion Date: Summer 2016

The contractor is preparing for final cleanup activities on this project to widen and resurface this portion of US 69.

US 79 Repairs and Resurfacing Project

  • Limits: From SH 204 to Mud Creek
  • Contractor: Reynolds & Kay
  • Cost: $5.7 million
  • Anticipated Completion Date: Summer 2017

Work on the subgrade continues in the westbound lanes. Expect lane closures for the remainder of the project when construction activities put equipment close to the travel lanes. Motorists are encouraged to avoid this location when possible. The roadway is being repaired and resurfaced. The speed limit has been reduced. Remember, traffic fines double when workers are present.

FM 22 and FM 23 Widening Project

  • Limits: From US 69 south of Jacksonville going SW to 1.5 miles west of FM 768 (Gallatin area); FM 23 from FM 343 to FM 1857
  • Contractor: Madden Contracting Company, LLC
  • Cost: $8.5 million
  • Anticipated Completion Date: Fall 2016

The contractor continues to install driveways on FM 23. Expect lane closures. These are safety projects designed to widen the roadways from 20’ to 24’ along a 4.2-mile section.

County Road Bridge Replacement Projects

  • Limits: CR 1707 at One Arm Creek west of Rusk between FM 347 and FM 2138 and CR 2303 at One Eye Creek south of Rusk between FM 23 and FM 752
  • Contractor: Stateline Construction
  • Cost: $699,993.90
  • Anticipated Completion Date: Winter 2016

The contractor is conducting work on the abutments with both CR 1707 and CR 2303 remaining closed as new bridges and approaches are built. The closures will last for about six months.

GREGG COUNTY – Longview Maintenance continues overlay hot mix operations on FM 1844 between Spur 502/Judson Road and SH 300/Gilmer Road. Expect lane closures with flaggers and a pilot car providing traffic control. Once completed, the crew moves to Kilgore near the Traffic Circle at SH 135 intersection to make pavement repairs. Expect lane closures with flaggers providing traffic control.

Gregg County construction projects updates:

FM 2275 George Richey Extension (Segment I)

  • Limits: McCann Road west to SH 300 (Gilmer Road)
  • Contractor: East Texas Bridge, Inc.
  • Cost: $12.4 million
  • Anticipated Completion Date: Fall 2017

McCann Road is open to traffic requiring the traveling public to stop at the new “Stop” signs at George Richey before proceeding through the intersection. Meanwhile, the contractor is hauling embankment as utility relocation and right of way clearing activities continue on this new roadway construction to connect Gilmer and McCann roads.

This Segment I project includes constructing two bridges and a four-lane roadway with center left turn lanes from McCann Road to SH 300/Gilmer Road. Excavation, embankment, bridge construction, subgrade treatment, storm drains, hot mix asphalt, curb and gutter and sidewalk are all part of the new construction.

FM 2275 George Richey Extension (Segments II & III)

•        Limits: McCann Road to US 259

•        Contractor: East Texas Bridge, Inc.

•        Cost: $12.8 million

•        Anticipated Completion Date: Fall 2016

The outside southbound lane of Judson Road remains closed as the contractor makes tie-ins to the new FM 2275. The contractor continues construction of traffic signals, curb and gutter, and sidewalk work between McCann Road and US 259. Work also continues between Judson Road and US 259. This project is constructing a new roadway from McCann Road to US 259.

FM 449

  • Limits: US 259 to FM 2751
  • Contractor: Madden Contracting Company, LLC
  • Cost: $607,133.00
  • Anticipated Completion Date: Fall 2016

No work is planned this week on this project to widen FM 449 two feet on each side and apply an overlay as well as conducting culvert work on the west end of the project.

Loop 281 at FM 2087 Overpass

•        Limits: SH 31 to approximately one mile south of SH 31

•        Contractor: Longview Bridge and Road, Ltd., of Longview.

•        Cost: $13.2 million

•        Anticipated Completion Date: January 2017

With southbound traffic now on the new bridge and Sabine Street and FM 2087 open to traffic, the contractor continues the installation of illumination, curb and gutter, inlets, embankment, a new exit ramp for SH 31, and paving. This project is building a new overpass over the railroad crossing. Expect delays in the detour areas.

HENDERSON COUNTY – Athens Maintenance plans to conduct seal coat work on FM 1803 from SH 31 to FM 317 and on Loop 60 from US 175 to US 175. Elsewhere, contractors will perform ditch maintenance on SH 198 from SH 334 to RM 3054 as well as on FM 607 from Loop 60 to FM 317. Expect lane closures with flaggers providing traffic control at all work locations. 

Henderson County construction projects updates:

FM 317 Repair Project (Notice of Project Completion)

  • Limits: At Athens Fish and Game Lake Dam
  • Contractor: Fritcher Construction
  • Cost: $446,216.00
  • Anticipated Completion Date: Late Summer 2016

Repair work is complete and this roadway/bridge is open to traffic. The road closed in March 2015 due to a flood-related washout about three miles east of SH 31. Repairs are expected to be completed later this summer, weather permitting. The plans for the permanent repairs have been coordinated with the Corp of Engineers and the Texas Commission on Environmental Quality (TCEQ).

US 175 Widening Project (Phase I)

  • Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
  • Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
  • Cost: $39.2 million
  • Anticipated Completion Date: November 2018

The eastern portion of Loop 60 is closed through the summer for construction of the new westbound mainlanes on this project that expands US 175 from two lanes to a four-lane divided with a depressed median. Drivers should expect one lane carrying two-way traffic throughout the project limits as well as occasional day time lane closures. Drivers on adjacent county roads and FM 804 should anticipate a change in traffic flow due to the detour now requiring two-way traffic on US 175. Dirt and drainage work around Loop 60E in Larue to near Baxter is ongoing. The speed limit in the construction zone has been set at 55 mph so slow down because traffic fines double when workers are present. Phase I construction started April 6, 2015.

US 175 Widening Project (Phase II)

  • Limits: 1.1 miles east of Loop 60B at LaRue to 0.85 mile east of FM 315 at Poynor
  • Contractor: Sundt Construction, Inc.of San Antonio
  • Cost: $37.8 million
  • Anticipated Completion Date: Late Summer 2017

Night work is being conducted between the hours of 5 a.m. and 11 p.m., Monday–Friday. Dirt work continues around FM 315 south of Poynor and several other locations. Drainage work is also ongoing at locations throughout the project. Work on drill shafts for the bridge overpass in the eastbound and westbound travel lanes continues at FM 315S. As part of the new highway construction, a short stretch of CR 4401 has been permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 remains open with access from CR 4345/Camp Road.

This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.

US 175 Widening Project (Phase III)

  • Limits: 0.85 miles east of FM 315 in Poynor, southeast to .5 miles NW of SH 155 at Frankston
  • Contractor: A.L. Helmcamp, Inc.
  • Cost: $27.6 million
  • Anticipated Completion Date: Spring 2019

The contractor expects to continue installing and maintaining storm water control measures throughout the project limits. Lane closures are possible. This project is expanding US 175 from two lanes to a four-lane divided highway with a depressed median.

FM 315/FM 1616 Widening Project

  • Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
  • Contractor: Big Creek Construction, LTD, of Hewitt, Texas
  • Cost: $3.07 million
  • Anticipated Completion Date: Late Summer 2016

The construction widening project is ongoing with work to extend the cross structures. One-way traffic can be expected throughout the project limits with daily lane closures. FM 1616 is expected to be completed this summer. Final work is being performed on FM 315.

SH 31 Bridge Painting Project – Westbound at Trinity River/Eastbound at Cedar Creek

  • Limits: From just east of Cedar Creek to just west of the Trinity River
  • Contractor: Olympus Painting Contractors Inc., of Clearwater, Florida
  • Cost: $2.3 million
  • Anticipated Completion Date: Summer 2016

Work has resumed under the eastbound Cedar Creek Bridge necessitating daily lane closures in one travel lane. Delays should be minimal. Bridge decks have been completed on both the westbound Trinity River Bridge and the eastbound Cedar Creek bridges.

RUSK COUNTY – Henderson Maintenance resumes overlay operations on SH 64 between Loop 571 and FM 15 at the Smith County line. Expect the roadway to be reduced to one lane carrying two-way traffic with flaggers and a pilot car guiding traffic through the work zone.

Rusk County construction projects updates:

US 259 North Project 

  • Limits: From Star to Loop 571
  • Contractor: Madden Contracting Company, LLC
  • Cost: $4.3 million
  • Anticipated Completion Date: Fall 2016

Asphalt paving operations continue during the day on this 2.3 mile project that includes base repairs, mill and inlay of asphalt surface, applying a hot mix overlay, and upgrading the pavement markings. Expect alternating lane closures.

US 79 South Project

  • Limits: From Loop 571 in Henderson going southwest for 3.0 miles to FM 839
  • Contractor: Drewery Construction Co., Inc.
  • Cost:  $6.7 million
  • Anticipated Completion Date: Summer 2017

The contractor continues widening operations on this portion of US 79. Expect lane closures and delays with one-way traffic control. Flaggers and a pilot car will guide traffic through the work zone. Work continues to place embankment on the widened edges. The posted speed limit has been reduced to 60 mph throughout this work zone and is being enforced by DPS. The project includes widening the existing pavement and adding a center left turn lane resulting in a new asphalt surface when the job is completed.

FM 3135 Widening Project

  • Limits: 1.9 miles NE of US 79 (W of CR 222) north to 1.7 miles SW of FM 1251 (CR 262)
  • Contractor: Madden Contracting Company, LLC
  • Cost: $2 million
  • Anticipated Completion Date: Early Fall 2016

The contractor is currently conducting culvert work. Expect lane closures with flaggers providing traffic control. The project consists of widening the pavement and installing milled centerline rumble strips on this three-mile section of roadway.

FM 95 Widening Project

  • Limits: FM 1798 to SH 315
  • Contractor: Madden Contracting Company, LLC
  • Cost: $2.5 million
  • Anticipated Completion Date: Early Fall 2016

The contractor plans to install metal beam guard fence on the project this week. Expect lane closures with flaggers providing traffic control. The project is widening a four-mile section of the road and adding shoulders.

FM 1798 Overlay Project (Notice of Completion)

  • Limits: From US 259 to FM 225
  • Contractor: Madden Contracting Company, LLC
  • Cost: $1.8 million
  • Anticipated Completion Date: Late summer 2016

The contractor has completed construction work on this project but continues to perform final close out activities. The project consisted of placing an asphalt overlay on the roadway.

SH 43 Overlay Project

  • Limits: From four miles south of FM 2658 to FM 3231
  • Contractor: Madden Contracting Company, LLC
  • Cost: $4.6 million
  • Anticipated Completion Date: Fall 2016

No work is scheduled this week. The project consists of placing an asphalt overlay on the roadway, base repairs, and new metal beam guard fence. 


SMITH COUNTY – Tyler Maintenance plans to conduct hot mix overlay work on FM 2710 between Lindale and FM 14 while another crew resumes edge repairs on FM 1995 between SH 110 and the Smith County line. Expect lane closures with flaggers providing traffic control.

Smith County construction projects updates:

Loop 323 West Widening at UPRR Underpass

•        Limits: Tylers West Loop and SH 31

•        Contractor: Longview Bridge and Road, Ltd., of Longview

•        Cost: $12 million

•        Anticipated Completion Date: Winter 2016

The contractor is preparing to restripe Loop 323 at SH 31. Some traffic shifting may be necessary as medians are installed north of SH 31. Work continues on sidewalks as well. The project includes widening Loop 323 from SH 31 to Shaw Street. The speed limit on Loop 323 in the work zone has been reduced to 45 mph from SH 64 to Shaw Street.

SH 31E Widening Project

•        Limits: From FM 757 to FM 2012

•        Contractor: Reynolds & Kay, LTD

•        Cost: $7.8 million

•        Anticipated Completion Date: Summer 2017

Work continues on the westbound passing lanes. Expect lane closures on this project designed to add passing lanes for multiple sections of roadway in both the eastbound and westbound directions. Once the widening is complete, a seal coat and final surface will be applied. A daily construction speed limit of 60 mph is in place when work is being performed.

SH 64

•        Limits: from Chapel Hill to Arp

•        Contractor: Drewery Construction of Nacogdoches

•        Cost: $3.9 million

•        Anticipated Completion Date: Summer 2016

Final work is being performed on this project to add passing lanes between FM 2607 and Arp. Expect lane closures.

FM 1253 Widening Project

  • Limits: From County Road 462 south, 1.3 miles north of FM 857 south to FM 1805; FM 1804 from Wood County line to US 69; FM 2015 from CR 313 to FM 16
  • Contractor: Longview Bridge and Road, Ltd., of Longview
  • Cost: $7.5 million
  • Anticipated Completion Date: Fall 2016

The contractor continues slope work on FM 1804 along with placing riprap along the Sabine River Bridge. Work on FM 2015 includes replacing mailboxes. No activity planned for FM 1253 this week. Expect lane closures. This contract consists of widening, sealing and resurfacing all three roadways.                       

Spur 248 Widening Project

  • Limits: From 1.75 miles west of FM 848/Old Omen Road going east to SH 64 southeast of Tyler
  • Contractor: Lonestar Equipment Company, Inc.
  • Cost: $8.6 million
  • Anticipated Completion Date: Summer 2018

The contractor resumes work on the eastbound lanes including retaining walls and storm drains. Expect lane closures. The speed limit has been reduced to 55 mph during construction. This project will widen Spur 248 from two lanes to a four-lane divided roadway with flush median.

County Road Bridge Replacement Projects

·        Limits: CR 4129 at Mud Creek near Lindale; CR 3104 at Prairie Creek north of FM 1252 near Winona; and CR 2138 at Blackhawk Creek south of Whitehouse

·        Contractor: Pierce Construction

·        Cost: $947,000.00

·        Anticipated Completion Date: Summer 2017

CR 2138 near Whitehouse is set to close Monday, September 12, with work to remove and replace the existing bridge getting underway September 19. County Roads (CR) 3104 and CR 4129 are already closed as work to build new bridges and approaches progresses. Each road will be closed for about six months.

US 271 Repairs and Resurfacing Project

  • Limits: From FM 2015 southward to Oakwood Street/Spur 147 in Tyler
  • Contractor: Reynolds & Kay
  • Cost: $4.3 million
  • Anticipated Completion Date: Fall 2016

Expect daily lane closures as seal coat operations continue on this 4.5-mile project to repair and resurface the roadway. Use alternate routes if possible to avoid delays.

I-20 Resurfacing Project

  • Limits: Eastbound lanes from FM 14 eastward to US 271
  • Contractor: Clark Construction
  • Cost: $2 million
  • Anticipated Completion Date: Fall 2016

The contractor is implementing a mobile operation to conduct final work which includes removing temporary striping on this project to resurface a 4.8-mile stretch of I-20. Lane closures are possible. 

VAN ZANDT COUNTY – Canton crews continue mill and inlay operations on US 80 just west of Grand Saline. Expect lane closures with flaggers providing traffic control.

Van Zandt County construction projects updates:

SH 198 Widening Project

  • Limits: from SH 243 in Canton southwest to 0.4 miles northeast of FM 316 near Phalba
  • Contractor: Big Creek Construction, Ltd., of Waco
  • Cost: $5 million
  • Anticipated Completion Date: Fall 2016

The contractor continues striping, placing reflectorized pavement markings and working on cleanup operations on this widening job. Expect lane closures during these moving operations.

FM 316 Widening Project

  • Limits: From FM 1256 south to FM 3080
  • Contractor: Big Creek Construction, Ltd., of Hewitt
  • Cost: $255,474.00
  • Anticipated Completion Date: Fall 2016

The contractor continues striping the roadway and placing reflectorized pavement makings. No lane closures expected on this widening project which also includes installing safety end treatments and advance warning signs.

FM 314 Widening Project

•        Limits: from I-20 to the Van Zandt/Henderson County line

•        Contractor: A.L. Helmcamp, Inc., of Buffalo

•        Cost: $11.9 million

•        Anticipated Completion Date: Summer 2018

Work continues to extend the cross structures and install driveway pipe between SH 64 and I-20. The contract also includes rehabbing the road north of SH 64 and laying hot mix for driveways south of SH 64. Expect lane closures.

FM 279 Resurfacing Project

•        Limits: from FM 858 in Ben Wheeler east to FM 314 in Edom

•        Contractor: APAC – Texas

•        Cost: $2.3 million

•        Anticipated Completion Date: Fall 2016

Vegetation maintenance continues as the contractor conducts cleanup activities on this job between Edom and Ben Wheeler. Expect lane closures.

FM 1256

•        Limits: from FM 316 eastward to SH 19

•        Contractor: Longview Bridge and Road, Ltd.

•        Cost: $5.8 million

•        Anticipated Completion Date: Fall 2018

Work to extend the cross structures continue on both sides of the roadway along the project limits. The project is widening almost eight miles of the roadway. No lane closures.

County Roads Bridge Replacement Projects

•        Limits: CR 3105 at Crooked Creek, CR 3809 at Negro Creek, CR 4404 at Cream Level Creek, and CR 2908 at Purtis Creek

•        Contractor: Stateline Construction, LLC.

•        Cost: $1.4 million

•        Anticipated Completion Date: Summer 2017

The contractor is building the new bridge on CR 3809 with a detour bridge in place. No lane closures planned.

WOOD COUNTY – Mineola Maintenance continues work on several roads around the county. Ditch maintenance is scheduled for SH 37 north of Mineola; base repairs being conducted on FM 1254; and pavement leveling on FM 514. Expect lane closures with flaggers directing traffic at all work locations.

I-20 Total Maintenance Contract

  • Limits: Gregg, Smith and Van Zandt counties
  • Contractor: Fireman Excavating

Routine maintenance activities are ongoing on I-20 with moving operations throughout the week:

-        Debris Removal: Monday and Thursday from the inside lane through all three counties

-        Debris Removal: Tuesday and Friday from the outside lane through all three counties

-        Installing Buttons: Mainlanes through all three counties

No lane closures planned but that is subject to change

  • NewsMore>>

  • Another team in Gilmer deserves attention, Union Hill is on a roll

    Another team in Gilmer deserves attention, Union Hill is on a roll

    Tuesday, November 21 2017 10:35 PM EST2017-11-22 03:35:41 GMT
    Union Hill captured its first undefeated regular season since 1982.Union Hill captured its first undefeated regular season since 1982.

    When the town of Gilmer is mentioned in relation to sports, the Buckeyes powerhouse football program immediately comes to mind. And that's fair considering they have won three state titles and racked up 13 double digit win seasons since 2000. But a small 1A school about nine miles away deserves some attention these days as well.

    More >>

    When the town of Gilmer is mentioned in relation to sports, the Buckeyes powerhouse football program immediately comes to mind. And that's fair considering they have won three state titles and racked up 13 double digit win seasons since 2000. But a small 1A school about nine miles away deserves some attention these days as well.

    More >>
  • Elkhart native Jeffrey Wilson out at least next two games, possibly done for year

    Elkhart native Jeffrey Wilson out at least next two games, possibly done for year

    Tuesday, November 21 2017 10:23 PM EST2017-11-22 03:23:47 GMT
    Wilson celebrates after scoring a touchdown.Wilson celebrates after scoring a touchdown.

    In other college football news, Elkhart native and North Texas running back Jeffrey Wilson scored two touchdowns and had over 70 rushing yards in UNT's win over Army on Saturday. The East Texan's senior campaign though is likely over. Wilson suffered an ankle injury in the victory and will not play against Rice or in next week's Conference USA championship game.

    More >>

    In other college football news, Elkhart native and North Texas running back Jeffrey Wilson scored two touchdowns and had over 70 rushing yards in UNT's win over Army on Saturday. The East Texan's senior campaign though is likely over. Wilson suffered an ankle injury in the victory and will not play against Rice or in next week's Conference USA championship game.

    More >>
  • What’s open on Thanksgiving in East Texas

    What’s open on Thanksgiving in East Texas

    Tuesday, November 21 2017 10:15 PM EST2017-11-22 03:15:12 GMT

    What’s opened, closed on Thanksgiving in East Texas If you plan on eating out on Thanksgiving instead of cooking up a big feast, here’s a list of restaurants that will be opened.

    More >>

    What’s opened, closed on Thanksgiving in East Texas If you plan on eating out on Thanksgiving instead of cooking up a big feast, here’s a list of restaurants that will be opened.

    More >>
Powered by Frankly