Lufkin Road Construction

In addition to today's (6-4-03) construction at 59 north and loop 287... Improvements will be made to the entrance and exit ramps and the u-turns at loop 287 and highway 103 east. That work will begin around june 11th.

On the june 18, they're expected to work on entrance and exit ramps at lufkin avenue and loop 287, as well as the frontage roads between fm 325 and fm 841.

Around july second, the frontage roads, intersections, and ramps will be improved at loop 287 and highway 59 south.

And on july 9th, work will be performed at night to improve the intersection of loop 287 and south first street.

Tex-dot will also make improvements to the area between k-mart and the lufkin mall.

Upcoming roadwork:

Road construction
around June 11
Loop 287 and Highway 103 east

Road construction
around June 18
Lufkin Avenue at Loop 287

Road construction
around July 2
Loop 287 at Highway 59 South

Road construction
around July 9
South First Street at Loop 287